Phase 1 of the road resurfacing project, covering the section from Hutt’s Gate to Halley’s Mount, began last week. Slurry surfacing commenced on Thursday, 12 November 2026. Subject to favourable weather conditions, the Roads Section aims to complete this phase by the end of this week.
Preparatory works for Phase 2, covering the section from W-Road to Lemon Tree Gut, are scheduled to begin this week. Slurry surfacing is planned to commence on Monday, 23 November 2026.
Daytime road closures will be in place for both Phases 1 and 2 between 09:00 and 15:00. Please refer to the map below for details of the road closures.

Motorists and residents are advised to plan their journeys accordingly and follow all road signs and traffic management measures in place during the works.
The public are thanked for their patience and cooperation while these works are carried out. The improvements will help provide better road conditions and safer, more efficient travel for all road users.